System-Level Construction Schedule [Energy] Law and Legal Definition
According to 10 CFR 950.3 [Title 10 Energy; Chapter III Department of Energy; Part 950 Standby Support for Certain Nuclear Plant Delays; Subpart A General Provisions], System-Level Construction Schedule means “an electronic critical path method schedule identifying the dates and durations of plant systems installation (but excluding details of components or parts installation), sequences and interrelationships, and milestone dates from commencement of construction through full power operation, using software acceptable to the Department.”